Shimla, Nov. 5
Deciding a dispute over construction of a property in State capital Shimla State Real Estate Regulatory Authority (RERA) slapped penalty of Rs 6 lakh on the construction company of BJP MLA from Chopal Balbir Singh Verma in the alleged denial of covered parking to flat buyers at Verma Apartments in Upper Malyana, outskirt of this capital town recently
The Authority has also directed the company to provide covered parking to all three complainants in accordance with the approved building plan within 60 days and deposit the penalty amount in the RERA fund within the same period.
The decisions were pronounced by a bench comprising RERA Chairman R.D. Dhiman and Member Vidur Mehta in three separate complaints filed by Vaibhav Gupta, Sanjay Kumar and Umesh Walia.
The complainants had booked three-bedroom apartments, each measuring approximately 1,200 square feet, at Verma Apartments in 2016. Each buyer had paid an advance of Rs 5 lakh at the time of booking.
According to the complainants, the company had promised covered parking facilities under the terms of their agreements. However, instead of providing covered parking inside the building, they were allotted parking spaces outside the building in the setback area.
Also Read Shimla- RERA questions setback rules along Natural Nallahs
The buyers also raised objections to the CGI sheet roofing installed over the parking spaces, alleging that the arrangement did not conform to the approved building plan and the commitments made in their agreements.
During the proceedings, the company contested the allegations and submitted that the agreement signed in 2025 was final. It maintained that parking outside the apartment building had been arranged at the request of the three flat buyers.
The company further submitted that the competent authority had raised objections to the sheds constructed in the setback area and that these structures were subsequently removed. It also contended that the Municipal Corporation, Shimla, had objected to the covered parking arrangements, leading to the removal of the parking sheds.
After examining the agreements and the approved building plan, RERA held that the buyers were entitled to covered parking inside the building in accordance with the sanctioned plan.
Though main case is still going on but the Authority(RERA) directed the company to fulfil its contractual obligations by providing covered parking to all three flat owners within 60 days. It also ordered the deposit of the cumulative penalty of Rs 6 lakh within the stipulated period.
Highly placed sources in the authority confirmed that the main fine is still to be decided as even other irregularities in the said project are being examined.
RERA has warned that failure to comply with its directions could invite further proceedings under Section 63 of the Real Estate (Regulation and Development) Act, 2016.
Himachal ki har badi khabar, sabse pehle aapke paas
Breaking news, local updates aur exclusive stories — seedha WhatsApp ya Email par. Free. No spam.
WhatsApp Alerts
Instant news seedha aapke phone par. Ek click me subscribe karein.
Subscribe on WhatsAppEmail Newsletter
Har nayi post ka link aapke inbox me. Kabhi bhi unsubscribe karein.